Fruitgrowers Dam Outlet Gate Improvements Project
Meeting #4 Agenda
December 13, 2023
10:00 a.m.
KGCI Project Reference #: 132
Call in Number: 1-888-633-0347 Passcode: 72888364
Attendees
Applegate Group: Craig Ullmann, Steven Morris
OCID: Mitch Thomas, Niles Riese, Jeff Widener
Bureau of Reclamation: Josh Dunham, Matt Bryner, Thomas Hook
Delta Conservation District: Suzie Bilberry
KGCI: Kyle Kissner, Jaime Jordan
Agenda
Tasks Previously Completed
- The following submittals were approved last week:
- 35 22 16-1 Product Data for Fresno Slide Gate
- Additional information on stem extension, stem supports, and operation pedestal forthcoming
- Product data for gearbox and actuators forthcoming
- 03 20 00-1 Concrete Reinforcing Revised
- OCID selected colors for roof panels (taupe) and Versetta Stone (ledgestone terra rosa).
- 35 22 16-1 Product Data for Fresno Slide Gate
- Submittals awaiting approval:
- 22 13 19-1 Ventilation System (sent 12/12)
Work Completed
- November Pay App submitted on 12/4
- Installed 9” bolts at downstream flanges
- Sandblasting cleanup completed.
- Completed spool installation.
- Located waterline for installation of new electrical power poles.
- Water samples submitted to Kephart & Co. for testing on 11/17 and 11/21.
- Results from 11/17 sample are as follows:
- pH 7.77 (acceptable range is 6.5-9)
- Total suspended solids 1440 mg/l (acceptable range is 30-45 mg/l). Over limit due to muck/ silt material. Will submit explanation with NetDMR.
- Results from 11/21 sample forthcoming. Will include uranium, solids (total dissolved), pH, solids (total suspended), arsenic, iron (total recoverable), iron (dissolved), manganese, selenium.
- We expect total suspended and total dissolved solids to be over limit due to muck/silt material. Expecting all other results to be within normal ranges.
- Results from 11/17 sample are as follows:
- Project cost modifications submitted on 12/13 for additional work and/or change in scope.
- Updated project schedule submitted on 12/13.
Installation of Remaining Hardware @ Complete Pipe Section.
2 Week Look Ahead:
- Order approved Fresno slide gate.
- Rebar for slab expected to be completed by Thursday 12/14.
- Primer/paint due to be in on Thursday 12/14.
- Primer & Paint installed either 12/15 and 12/19.
- Dremel cleanup on underside of pipe before primer & paint application.
- Schedule with Applegate/Bureau for week of 12/18 to exercise valves.
- Schedule with DMEA for installation of power poles once 299 is completed.
- Grading, compaction, formwork, installation of structural reinforcement and placement of concrete for building slab expected to completed before 12/22.
- Doughty Steel sent materials to be galvanized. Expect completion by sometime next week.
- High Country Manufacturing to continue fabrication of machine components.
- Forthcoming submittals:
- 02 83 33-2 Bills of Lading for Misc. Metals
- 02 83 33-5 Remaining Metalwork Inspection Report
- 22 13 19-1 Ventilation System
- 35 22 16-1 Remaining information for slide gate, product data for manual operator gearbox and motorized actuator