Fruitgrowers Dam Outlet Gate Improvements Project
Meeting #7 Agenda
January 3, 2024
10:00 a.m.
KGCI Project Reference #: 132
Call in Number: 1-888-633-0347 Passcode: 72888364
Attendees
Applegate Group: Craig Ullmann, Steven Morris
OCID: Mitch Thomas, Niles Riese, Jeff Widener
Bureau of Reclamation: Josh Dunham, Matt Bryner, Thomas Hook, Phil Ipson
Delta Conservation District: Suzie Bilberry
KGCI: Kyle Kissner, Jaime Jordan
Agenda
Tasks Previously Completed
- Parts lists received:
- Gate house, shaft & gate chamber layout (270-417-256)
- Self retracting lifelines
- Shaft deck assembly (270-417-258)
- Roof hatch expected _ship 2/16/24_______
- Chamber landing and shaft guide & pipe hangar assemblies (270-417-263)
- Sprocket covers and drive assembly (270-417-269)
- Valve actuator assembly (270-417-272)
- Bolt assemblies (270-417-279)
- Gate house, shaft & gate chamber layout (270-417-256)
Work Completed
- Placement of concrete for building slab on 12/21.
- Picked up materials for ventilation system from Bolinger & Queen on 12/20. Placed vent pipe section shaft approxi-mately 10’.
- Submitted NetDMR report on 12/28. Dewatering permit terminated.
- Picked up primer/paint on 12/20. Dremel cleanup on underside of pipe before primer & paint application. Applied two coats of primer before applying final top coat on 12/29.
- Due to the amount of material within the pipe and at the inlet/outlet sections of the pipe, opted to wait to exercise valves. KGCI will get with Southwestern Systems to get a quote on removing material from stilling basin next week.
- Bryan met with Niles and Jeff concerning cleaning out the pond at Dairy. Submit quote by end of this week.
2 Week Look Ahead:
- Order approved Fresno slide gate (awaiting approval for submittal sent 1/2).
- Submit December billing today (1/3/24)
- Submit updated schedule by the end of this week.
- Order actuators (awaiting information from B&Q for Bettis manufacturer).
- Spoke with Shelby Bear and Phil Sanchez from DMEA re: installation of power poles. DMEA is going to verify staking hopefully by the end of day to day. Once verified, they will let us know when they anticipate being onsite.
- Begin erection of equipment building.
- Doughty Steel fab galvanization completed; ready for pickup _1/9/24______. High Country Manufacturing to continue fabrication of machine components.
12/21/23—Double mat of rebar and placement of concrete
12/21/23—Concrete placement w/ light broom finish
12/28/23—Sanding second coat of primer at existing pipe section
12/29/23—Placement of final paint coating
Parts list items received.