Fruitgrowers Dam Outlet Gate Improvements Project
Meeting #14 Agenda
February 21, 2024
10:00 a.m.
KGCI Project Reference #: 132
Call in Number: 1-888-633-0347 Passcode: 72888364
Attendees
Applegate Group: Craig Ullmann, Steven Morris
OCID: Mitch Thomas, Niles Riese, Jeff Widener
Bureau of Reclamation: Josh Dunham, Matt Bryner, Thomas Hook, Phil Ipson
Delta Conservation District: Suzie Bilberry
KGCI: Kyle Kissner, Jaime Jordan
Agenda
Work Completed
- Sent quote to OCID & Applegate for review pertaining to installation of 250 LF of conduit for Circle Ditch Monitoring.
- Requested quote for slide gate from Fresno and Watch Technologies. WT cannot fabricate the type of gate needed. Awaiting pricing from Fresno through Bolinger & Queen. Should have quote by end of this week and will put together complete estimate for installation for Applegate and OCID to review.
- Picked up roof metal package. Began installation. Missing 2 runs of facia metal that we will receive on 2/28/24. Install same day to complete metal roof.
- Finished removing ladder and installed new ladder. Removed ring @ shaft. Installed cover. Will completely secure cover once all brackets are lasered in.
- Installation of shaft guides and pipe hangar weldments today.
- Called Steven at DMEA yesterday to schedule power line installation to panel weather head. Hope to hear back from DMEA today.
- Talked to Bray on L3 Bolts earlier this week. He assured me that L3 Bolts are 1-1/4” #8 UN. May be coating thickness at threads causing issue. Will install this week.
2 Week Look Ahead
- White Star Electric onsite to install conduit in shaft tomorrow.
- Finish fabrication of connection between actuator drive bushing and motorized actuator drive shafts. This should complete all shaft/stem weldment fabrication.
- Continue installation of building exterior finishes.
- Continue installation of fabricated materials, hardware and accessories & vent piping.
Cover Set in Place
Removing Existing Ladder
February 20, 2024 - Wick Pond
New Ladder Installed
West Section of Soffit Installed, Flashing on North Side
Roof Panels Starting to be Installed with Boot at Weather Head