Fruitgrowers Dam Outlet Gate Improvements Project
Meeting #11 Agenda
January 31, 2024
10:00 a.m.
KGCI Project Reference #: 132
Call in Number: 1-888-633-0347 Passcode: 72888364
Attendees
Applegate Group: Craig Ullmann, Steven Morris
OCID: Mitch Thomas, Niles Riese, Jeff Widener
Bureau of Reclamation: Josh Dunham, Matt Bryner, Thomas Hook, Phil Ipson
Delta Conservation District: Suzie Bilberry
KGCI: Kyle Kissner, Jaime Jordan
Agenda
Work Completed
- Ordered integrated slide gate and actuator from Watch Technologies. Expected ship date: first week of April. If they have an opening they will fit in to ship sooner.
- Ordered motorized actuators. First one expected within a week, second one by end of February.
- Doughty completed fabrication of adaptor plates. Picked up on Monday.
- High Country fabricating drive shaft revised for dimensions of motorized actuators. All fabrication expected to be complete in the next 2 weeks.
- Confirmed dimensions of Circle Ditch equipment enclosure and breaker with White Star. Waiting on revised submittals.
- White Star Electric began rough-in. Expect rough-in inspection on Friday 2/2/24.
- Set equipment building on slab and platform in shaft. Cut out bottom section of ladder. Completed framing and installed ice and water shield. Building is dried in.
- DMEA finished running powerlines.
- Excavated for installation of Circle Ditch pole and irrigation box. Set box.
- Picked up Versetta Stone.
2 Week Look Ahead
- Run conduit at Circle Ditch. Install NEMA Enclosure on galvanized pole after pouring in place.
- Continue to install fabricated materials in shaft, hardware and accessories. Installation of new ladder and shaft brackets.
- Hydrovac scheduled for this morning at stilling basin.
- Will start pond work at Wick Dairy today. Hope to complete before weather sits in on Friday.
- High Country Manufacturing to continue fabrication of machine components. Should start seeing shaft pieces by end of next week.
- After electrical inspection, insulate and start installing building finishes on interior and exterior as week as well as installation of door and window.
January 25, 2024 — Setting equipment building.
January 30, 2024 — DMEA Onsite to Set Last Pole & Run Powerline
January 30, 2024 — Building Dried-In
Meeting Questions
The remaining time is available for questions.