January 31, 2024 Agenda

Fruitgrowers Dam Outlet Gate Improvements Project

Meeting #11 Agenda
January 31, 2024
10:00 a.m.

KGCI Project Reference #: 132
Call in Number: 1-888-633-0347 Passcode: 72888364

Attendees

Applegate Group: Craig Ullmann, Steven Morris

OCID: Mitch Thomas, Niles Riese, Jeff Widener

Bureau of Reclamation: Josh Dunham, Matt Bryner, Thomas Hook, Phil Ipson

Delta Conservation District: Suzie Bilberry

KGCI: Kyle Kissner, Jaime Jordan

Agenda

Work Completed

  • Ordered integrated slide gate and actuator from Watch Technologies. Expected ship date: first week of April. If they have an opening they will fit in to ship sooner.
  • Ordered motorized actuators. First one expected within a week, second one by end of February.
  • Doughty completed fabrication of adaptor plates. Picked up on Monday.
  • High Country fabricating drive shaft revised for dimensions of motorized actuators. All fabrication expected to be complete in the next 2 weeks.
  • Confirmed dimensions of Circle Ditch equipment enclosure and breaker with White Star. Waiting on revised submittals.
  • White Star Electric began rough-in. Expect rough-in inspection on Friday 2/2/24.
  • Set equipment building on slab and platform in shaft. Cut out bottom section of ladder. Completed framing and installed ice and water shield. Building is dried in.
  • DMEA finished running powerlines.
  • Excavated for installation of Circle Ditch pole and irrigation box. Set box.
  • Picked up Versetta Stone.

2 Week Look Ahead

  • Run conduit at Circle Ditch. Install NEMA Enclosure on galvanized pole after pouring in place.
  • Continue to install fabricated materials in shaft, hardware and accessories. Installation of new ladder and shaft brackets.
  • Hydrovac scheduled for this morning at stilling basin.
  • Will start pond work at Wick Dairy today. Hope to complete before weather sits in on Friday.
  • High Country Manufacturing to continue fabrication of machine components. Should start seeing shaft pieces by end of next week.
  • After electrical inspection, insulate and start installing building finishes on interior and exterior as week as well as installation of door and window.

January 25, 2024 — Setting equipment building.

Setting equipment building

January 30, 2024 — DMEA Onsite to Set Last Pole & Run Powerline

DMEA Onsite to Set Last Poleand Run Powerline

January 30, 2024 — Building Dried-In

Building Dried-In

Meeting Questions

The remaining time is available for questions.